PROJECT : FOLK HOSTEL SUKHUMVIT 22

Updated: Aug 31, 2018


On site install H-beam for wall and Screening top slab 4th slab

Update Work 2018.05.04

- H-beam support for Wall

- Prepare Pipe for Drain System

- Wall construction 3FL. some part

- Prepare work wall construction & floor 4FL.

Update Work 2018.05.11

- Wall construction 3FL. & 4FL.

- Pipe For drain system complete

- Start install Wire way 3FL. & 4FL. for Electrical

- Start install Door frame some part

- H-beam 1FL.


Update work 2018.05.18

- Wall construction 3FL & 4FL Construction Work 80-90%

- Wall constrcution 2FL Constrction Work 70%

- Start drill wall for electric pipe

- Start Coring floor for system pipe

- Start structure work pound


Update work 2018.05.25

- Coring WD & S for all floor

- Drill wall electrical pipe

- Start pipe work 4FL.

Update work 2018.06.01

- Start metal steel floor4th

- block Lighting 4th

- work septic tank

- coring complete


Update work 2018.06.08

- Start Plaster wall level 4th floor

- electric pipe 4th floor

-install septic tank 1st floor

- install pipe air condition


Update Work 2018.06.15

- Wall work Floor 4th finish

- Electric Work Floor 4th 60%

- Pipe drain air and Exhaust Floor 4th

- Work Wall Floor 3rd 70-80%

- Back of house Floor 1st floor finish and pipe drain rain

- Pipe waste drain,soild,cold water Floor 3rd



Update Work 2018.06.29

- Wall work Floor 4th finish

- Electric Work Floor 4th 90%

- Pipe drain air and Exhaust Floor 4th

- Start work tile floor 4th

- Start work Wall back of house floor 1st

- Pipe waste drain,soild,cold water Floor 2-3rd

- ACU/FCU installation floor 4th

- Start Structure Ceiling Floor 60%



Update Work 2018.07.12

- Color Paint floor 4 finished

- test lighting and installation downlight and ceiling lamp

- Start work aluminium frame

- Start work vinyl floor 4


Update Work 2018.07.20

- Color Paint floor 3

- installation tank and pump complete

- aluminium frame finished

- work vinyl floor complete

- tile work toilet floor 2-3



Update Work 2018.07.31

- Color Paint floor 2-3

- Check Lighting Floor 2-3

- Prepare lighting and system floor 1

- Prepare Door entrance and window

- Roof back of house

Update Work 2018.08.03

- prepare floor 1 for vinyl

- Lighting Floor 1

- Start build-in Floor 2-3

Update Work 2018.08.10

- Built-in furniture Floor 2-3

- Install frame door and window floor

- Wall kitchen

- Lighting floor 1

- Work color floor 3




Update Work 2018.08.16

- Built-in furniture Floor 1-2

- Color paint floor 1

- Start vinyl floor 3

- Lighting floor 1



Update Work 2018.08.27

- Built-in furniture Floor 1-2

- Color paint

- vinyl floor 2-3

- Lighting complete

- edit defect work


Update Work 2018.08.31

- Built-in furniture Floor 1-4 - edit defect work